Mackworth

Client: Miller Homes & Redrow Homes
Scope: Residential infrastructure for a large-scale 600-home residential development, including adoptable Roads & Sewers

Programme: 9 months

T Balfe Construction Ltd

Additional Information

Quantity
Approx. 19,500m² of Roads and Sewers delivered

Drainage
Foul and Surface Water systems installed, with excavations up to 7m deep

Pipe Sizes
150mm to 1200mm diameter

Roads
Section 38 adoptable Roads constructed

Drainage Adoption
Section 104 adoptable drainage delivered

Outfalls
Section 106 outfall connections completed

Highways
Section 278 highway works delivered

Utilities
Coordination and installation of HV, LV, Water, Gas, BT, and Virgin services

Footpaths
Construction of footpaths, including kerbs and edgings

Plot Works
Foundations, external drainage, and external surfacing, including patios, paving, and driveways

Works Included
Earthworks, deep drainage, attenuation, and external works

Delivery
Phased delivery aligned with the construction build route

Standards
Built to adoptable specifications (S38 / S104 / S278)

Key Focus
Programme management, stakeholder coordination, and safe delivery